GARUN Process Engineering
Design & engineering

The plant is built twice.
The first time on paper.

Before a foundation is poured, the whole plant exists as a design basis, a mass balance, a P&ID and a set of drawings that a site can build from. That is the part of the job we are actually good at — and the part that decides whether the plant runs at rate in its first month or its third year.

Design stages4Drawings per line180–260Issue formatsDWG · PDF · STEPTypical programme12–16 weeks
General arrangement drawing of a lined reaction vessel with nozzle orientation and dimensions
Design & engineering
01 / Design basis

Everything starts with one document.

The design basis is a short document — usually six to ten pages — that fixes what the plant must do and what it must do it with. Every drawing after it is a consequence.

We write it together with the client before any drawing is started. It records the product and grade, target output and shift pattern, raw material assay and source, site conditions, utilities, discharge limits and the standards the plant must meet. It is signed by both parties. When a question comes up in month seven — and it always does — the answer is in that document, not in somebody's memory of a meeting.

SubjectWhat the basis fixesWho provides
ProductGrade, Al2O3 content, solid or liquid, packagingClient
CapacityTonnes per year, batches per day, shift pattern, design marginClient + GARUN
Raw materialAlumina source, acid concentration, assay, impurities, delivery formClient
SiteLocation, dimensions, plot plan, soil bearing capacity, flood levelClient
UtilitiesPower (kV, kVA), steam (pressure, t/h), water, compressed air, drainageClient + GARUN
EmissionsStack limits for HCl and particulates, noise, effluent limitsClient / authority
StandardsPressure, structural, electrical and safety codes to be appliedClient + GARUN

Where the client cannot supply a figure, we state the assumption in writing and flag it as a design risk. Assumptions that stay hidden are what turn into variation orders.

Why this matters commercially: a design basis that is agreed in week one is the cheapest change-control mechanism available. Without it, every scope argument is settled by whoever is more tired.
02 / Design depth

Four stages, four sets of drawings.

Each stage ends with a defined deliverable and a client approval gate. Nothing moves to the next stage until the previous one is signed off — which is how a project stays on schedule instead of unravelling in the last month.

STAGE 01

Concept & feasibility

Week 1-2

Route selection, capacity model and a plot plan. We compare the acid route against alternatives on capital, operating cost and product quality.

  • Design basis
  • Block flow diagram
  • Capacity & cost model
  • Plot plan option study
STAGE 02

Basic engineering

Week 3-6

The process is frozen here. Mass and heat balance, PFD, equipment list and datasheets that are firm enough to send out for quotation.

  • Mass & heat balance
  • PFD
  • Equipment list & datasheets
  • Utility summary
STAGE 03

Detailed engineering

Week 6-14

Every drawing the site builds from, produced from a 3D model and clash-checked before release. Vendor data is incorporated, not assumed.

  • P&ID & GA
  • Foundation loads
  • Piping isometrics
  • Electrical & control
STAGE 04

As-built & handover

At commissioning

Drawings corrected to what was installed, with test records and the O&M manual, bound into a handover set the client can operate from.

  • As-built register
  • Test records
  • O&M manual
  • Spare parts list
03 / The drawing set

What 200 sheets actually contain.

A drawing set is not a pile of paper — it is an indexed, revision-controlled package in which every sheet has a number, a purpose and a status.

GR-PFD-001Process flow diagramEvery stream with flow, temperature, pressure and composition; the basis for the mass balance and the utility summary.A1 / PDF
GR-PID-010…019Piping & instrumentation diagramsLine numbering, instrument tags, control loops, interlock philosophy. One sheet per process area, not one for the whole plant.A1 / DWG
GR-GA-101/102General arrangement — plan and sectionsEquipment layout with maintenance access, operator routes, escape routes and future expansion space shown.A1 / DWG
GR-EQ-201…212Equipment general arrangement drawingsOne per equipment tag: dimensions, nozzle schedule, support loads, lining and insulation. The drawing a fabricator builds from.A1 / DWG
GR-FD-301/302Foundation layout and load tableAnchor bolt layouts, embedded plates, static and dynamic loads, grout details. What the civil contractor needs, in the form they need it.A1 / DWG
GR-ST-401Structural steel and platform scheduleBeam sizes, connection details, handrail and access platforms for elevated equipment.A1 / DWG
GR-PI-501…5xxPiping isometricsOne per line: spool breakdown, bill of materials, weld numbering, support locations. This is what makes site piping quick.A3 / DWG
GR-EL-601/602Single-line diagram and cable scheduleLoad list, breaker sizing, cable routes, earthing. Issued with the motor list so the client can order cable locally.A1 / DWG
GR-IC-701Instrument index and loop drawingsTag, service, range, alarm and trip settings, loop diagram for each control loop.A3 / PDF
GR-SP-801Equipment datasheetsOne per tag: duty, materials, design conditions, connections, inspection requirements.A4 / PDF
GR-AB-001As-built registerRevision index against the issued-for-construction set, with every change recorded and every red-line markup closed out.A4 / PDF

The register above is the core. A live project also carries utility distribution, insulation and painting schedules, lifting plans for heavy vessels, a safety and hazard review record, and the commissioning procedures — typically another forty to sixty sheets.

Revision control: every sheet carries a revision code and a status — IFR (issued for review), IFD (for design), IFC (for construction), AB (as-built). A drawing without a status is a drawing nobody should build from.
04 / Review gates

How a drawing gets approved.

Four review points, each with a defined deliverable and a fixed comment period. This is the discipline that keeps a design honest.

  1. 01

    30% review — layout and process

    PFD, plot plan, equipment list and the first GA. The client confirms the process route and the space allocation before anything is detailed. Comment period: 5 working days.

  2. 02

    60% review — mechanical and civil

    Equipment GA drawings, foundation loads and the structural concept. The civil contractor can start here, which is usually the real schedule constraint.

  3. 03

    90% review — everything else

    P&ID complete, piping isometrics, electrical and instrumentation. This is the last point at which a change costs engineering time rather than steel.

  4. 04

    IFC release — issued for construction

    Signed, stamped and released to site. Every later change becomes a revision with a cost and schedule consequence, recorded in the register.

Internally every discipline drawing passes a check by a second engineer before it reaches the client. Calculations are filed with the drawing they support, so the reason for a 1,500 mm nozzle elevation is traceable three years later.

A drawing set that cannot be checked is not a design, it is an illustration.GARUN engineering practice
05 / Model & coordination

Modelled, clash-checked, then drawn.

We build the plant as a 3D model first. Drawings are cut from the model, which means the plan, the section and the isometric cannot disagree with each other.

The model is used for three things beyond drawing production: clash detection between pipework, steel and equipment; extracting accurate bills of material so the procurement list matches the design; and walking the client through the plant before it exists. On overseas projects that last point saves an enormous amount of correspondence.

  • Clash check at 60% and again at 90%, with every collision resolved or accepted in writing
  • Nozzle orientation agreed with the vessel fabricator before the GA is released — not after the vessel is built
  • Maintenance envelopes drawn into the model: can the dryer drum be changed, can the impeller be lifted out
  • Neutral model export (STEP or IFC) available if the client wants to coordinate with their own civil and structural design
Common failure we design against: equipment bought before the layout is fixed. The nozzle ends up on the wrong side, the platform does not reach the manway, and the fix is a site modification instead of a drawing revision.
06 / The team

Who actually draws it.

A project team of five to eight people, led by one process engineer who stays with the job from the first call to the as-built set.

Process

Process engineer

Owns the design basis, the mass and heat balance and the P&ID. The single point of technical accountability for the whole plant.

Mechanical

Mechanical draughting

Equipment GA drawings, nozzle schedules, lining and insulation details, fabrication drawings released to the workshop.

Civil & structural

Layout and foundations

Plot plan, foundation loads, anchor layouts, steel and platform schedules, co-ordinated with the client's civil contractor.

E&I

Electrical and instrumentation

Load list, single-line diagram, cable schedule, instrument index, control philosophy and interlock schedule.

Piping is detailed by the same team that produced the GA, which is why the isometrics and the layout agree. On a turnkey project the site supervision comes from this team as well — the person answering the site query has usually drawn the sheet in question.

07 / Deliverables

What you receive, in what format.

DeliverableContentFormat
Design basisCapacity, materials, utilities, standards, assumptionsPDF
Mass & heat balanceStream table, utility consumption, yieldXLS / PDF
PFD & P&IDProcess flow, line and instrument numbering, control loopsDWG / PDF
General arrangementPlan, sections, maintenance access, expansion spaceDWG / PDF
Equipment drawingsGA per tag, nozzle schedule, support loadsDWG / PDF
Civil packageFoundation layout, load table, anchor and embedded platesDWG / PDF
Piping packageIsometrics, support schedule, bill of materialsDWG / PDF
Electrical packageLoad list, single-line diagram, cable and earthing scheduleDWG / PDF
Instrument packageIndex, datasheets, loop drawings, interlock schedulePDF / XLS
3D modelClash-checked plant modelSTEP / IFC on request
O&M manualOperating sequence, troubleshooting, spares, maintenance planPDF
As-built registerRevision index and closed-out red-line markupsPDF

Drawings are issued in English as standard. Metric dimensions; imperial conversion on request.

If you already have drawings, send them. We will comment on them before we quote — and tell you honestly if the design is fine and you only need equipment.Engineering first, commercial second